Eastern Freeway cost overrun Rs 259 crore: RTI

Written By Unknown on Jumat, 11 April 2014 | 22.23

MUMBAI: The third phase of the Eastern Freeway up to Ghatkopar, which may be thrown open to motorists this month, has witnessed a 23% increase in cost ever since work started in 2007.

"The project's cost rose from Rs 847 crore to Rs 1,106 crore because of delay in rehabilitation of project-affected people and slow execution of work," RTI activist Anil Galgali said.

Galgali had sought information about the Eastern Freeway project from the MMRDA . Work on the stretch between Chhatrapati Shivaji Maharaj Vastu Sangrahalaya to Anik Junctionwas scheduled to be completed by January 18, 2011 after the work order was issued in January 2008.

"There was a delay of 29 months in executing this phase of the project," Galgali added.

The RTI query revealed that the work on the Anik-Panjrapol Link Road has not yet been completed although it was opened in June 2013. The third phase (Panjrapol-Ghatkopar Link Road), which is slated for inauguration soon, has already missed the extended deadline of December 2013.

It was scheduled to be completed by February 2011 after the work order was issued in August 2009. The cost too has increased to Rs 293.84 crore from the original estimate of Rs 168 crore.


Anda sedang membaca artikel tentang

Eastern Freeway cost overrun Rs 259 crore: RTI

Dengan url

http://cegahkeropostulang.blogspot.com/2014/04/eastern-freeway-cost-overrun-rs-259.html

Anda boleh menyebar luaskannya atau mengcopy paste-nya

Eastern Freeway cost overrun Rs 259 crore: RTI

namun jangan lupa untuk meletakkan link

Eastern Freeway cost overrun Rs 259 crore: RTI

sebagai sumbernya

0 komentar:

Posting Komentar

techieblogger.com Techie Blogger Techie Blogger