The country's first Monorail service is commencing operations after a delay of over two years. This new addition to the city's public transport system will be made available for public use on Sunday.
The Rs 3,000-crore monorail project is being implemented in two phases. The first phase comprises the 8.9 km long Wadala-Chembur section, while in the second phase the services will be extended to Sant Gadge Maharaj Chowk in South Mumbai.
The Authority has fixed fares between Rs 5-11 for the first phase of operations, he said adding that MMRDA will operate six trains in the first phase, and another 10 will be added in the second.
To begin with, the services will operate with four coaches having a combined carrying capacity of 2,300 passengers at every 15 minutes, Madan said.
"We aim to provide a service at every four minutes going forward," he said.
The monorail project has been executed by a consortium of engineering major Larsen and Toubro Ltd (L&T) and Malaysian firm Scomi Engineering and owned and operated by MMRDA.
The monorail is expected to reduce the travel time between Wadala and Chembur by almost half, from 40 minutes at present to nearly 21 minutes.
MMRDA has already spent Rs 1,900 crore of the Rs 3,000 crore allocated for the project, Madan said adding, "the civil work on the second phase of the project has been completed."
(With inputs from PTI)
Anda sedang membaca artikel tentang
Maharashtra CM Prithviraj Chavan inaugurates monorail in Mumbai
Dengan url
http://cegahkeropostulang.blogspot.com/2014/02/maharashtra-cm-prithviraj-chavan_1.html
Anda boleh menyebar luaskannya atau mengcopy paste-nya
Maharashtra CM Prithviraj Chavan inaugurates monorail in Mumbai
namun jangan lupa untuk meletakkan link
Maharashtra CM Prithviraj Chavan inaugurates monorail in Mumbai
sebagai sumbernya
0 komentar:
Posting Komentar